Agenda Title:Approval of Change Order No. 1: EHS Albee Stadium/Bud Cloney Project
Meeting Date:August 29, 2024
Item:Consent


WHAT (the board is asked to discuss, receive, approve, or adopt)

The Governing Board is receiving notification of Change Order No. 1 for the EHS Albee Stadium/Cloney Field project.



WHY (briefly explain why the action or discussion is important; and if applicable, how it is connected to site, district, or strategic plans)
The justifications for Change Order No. 1 are delineated in the attached document.

STRATEGIC PLAN/PRIORITY AREA:
Priority Area 19: New and Modernized Facilities

HISTORY (list previous staff or board action(s) with dates if possible)

The Board approved the low bid awarding the Eureka High School Albee Stadium/Cloney Field project to Adams Commercial General Contracting, Inc. (ACGC) at the May 2, 2024 meeting and a 10% contingency fund was approved at the August 8, 2024 meeting.

HOW MUCH(list the revenue amount $ and/or the expense amount $)
Total additive cost for Change Order No. 1 is $8,836.91.

WHO(list the name of the contact person(s), job title, and site location)
Paul Ziegler, Assistant Superintendent of Business Services
ATTACHMENTS:
Description
Change Order No. 1