| WHAT (the board is asked to discuss, receive, approve, or adopt) |
The Governing Board is receiving notification of Change Order No. 1 for the EHS Albee Stadium/Cloney Field project.
|
|
| WHY (briefly explain why the action or discussion is important; and if applicable, how it is connected to site, district, or strategic plans) |
| The justifications for Change Order No. 1 are delineated in the attached document. |
|
STRATEGIC PLAN/PRIORITY AREA:
|
Priority Area 19: New and Modernized Facilities
|
HISTORY (list previous staff or board action(s) with dates if possible) |
The Board approved the low bid awarding the Eureka High School Albee Stadium/Cloney Field project to Adams Commercial General Contracting, Inc. (ACGC) at the May 2, 2024 meeting and a 10% contingency fund was approved at the August 8, 2024 meeting.
|
|
| HOW MUCH(list the revenue amount $ and/or the expense amount $) |
Total additive cost for Change Order No. 1 is $8,836.91.
|
|
| WHO(list the name of the contact person(s), job title, and site location) |
| Paul Ziegler, Assistant Superintendent of Business Services |